南寧東站站房結構設計
邱劍1,韓志偉2,溫四清1,葉志雄1
- 摘 要
-
邱劍1,韓志偉2,溫四清1,葉志雄1(1 中信建筑設計研究總院有限公司,武漢430014; 2 鐵道部工程設計鑒定中心,北京100844)[摘要]南寧東站采用線上式高架候車的大型橋建合一鐵路站房。其站臺層被3條正線分成4部分,到發(fā)線采用普通混凝土框架結構體系,正線橋采用地道式框架橋,提高了出站層的建筑凈空。高架候車層采用雙向預應力混凝土框架梁,減輕了結構自重,并對應于正線橋的位置設置2道結構縫,有效地降低結構的溫度作用。屋蓋采用鋼管混凝土柱支承的管桁架與網(wǎng)架相結合體系,結構布置安全、經(jīng)濟;而且結構和建筑形態(tài)、效果完全統(tǒng)一。天窗采用由鋼梁和鋼拉桿組成的屋架結構,結構受力合理又便于施工,實現(xiàn)結構與建筑的完美結合。結構計算與分析表明,結構體系傳力明確,具有良好的經(jīng)濟性和抗震性能。[關鍵詞]橋建合一;預應力混凝土梁;鋼管混凝土柱;管桁架;鋼拉桿中圖分類號:TU318文獻標識碼:A文章編號:1002-848X(2012)09-0010-04Structural design of the station building in Nanning East Railway StationQiu Jian1, Han Zhiwei2, Wen Siqing1, Ye Zhixiong1(1 CITIC General Institute of Architectural Design and Research Co., Ltd., Wuhan 430014, China;2 Appraisal Center of Engineering Design, Ministry of Railways, Beijing 100844, China)Abstract: As a large railway transportation hub, bridge-station combined structure with high elevated waiting hall is used to Nanning East Railway Station. The railway bridge structure floor is divided into 4 parts by 3 main line rails. Concrete frame structure system is adopted in the arrival and departure track, and tunnel type frame bridge is used in the main line track, which increases the headroom of the out station floor. The overhead waiting hall chooses two-way prestressed concrete beams, which reduces the weight of the structure. Two structural joints are set at the positions corresponding to the main line rails to reduce the temperature-induced internal forces. The combination structure of pipe truss and steel girder supported by concrete filled steel tubular column is used to the roof of the station, and the structure layout is economic and security. The roof truss structure which consists of steel bars and box beams is used to the skylight, this structure is simple and effectual, and easy for construction. The perfect combination of architecture and structure is realized too. Analysis and calculation indicate that the whole structure has good economy and seismic performance.Keywords: bridge-station combined structure; prestressed concrete beam; concrete filled steel tubular column; pipe truss structure; steel bar作者簡介:邱劍,教授級高級工程師,一級注冊結構工程師,Email:21244113@qq.com。參考文獻[1]邱劍,溫四清,熊巍,等.貴陽北站站房結構設計[J].建筑結構, 2012,42(9):1-5.[2]TB 10002 1—2005鐵路橋涵設計基本規(guī)范[S].北京:中國鐵道出版社,2008.[3]TB 10002 3—2005鐵路橋涵鋼筋混凝土和預應力混凝土結構設計規(guī)范[S].北京:中國鐵道出版社,2007.[4]GB 50011—2001建筑抗震設計規(guī)范[S].2008年版.北京:中國建筑工業(yè)出版社,2008.[5]GB 50111—2006鐵路工程抗震設計規(guī)范[S].北京:中國計劃出版社,2006.