- 摘 要
-
(1 河北工業(yè)大學(xué)土木與交通學(xué)院, 天津 300401; 2 河北省建筑科學(xué)研究院有限公司, 石家莊 050021)
[摘要]目前糾傾技術(shù)主要依靠過去經(jīng)驗(yàn)來指導(dǎo)工程實(shí)踐,以往的糾傾對象多為多層和低層建筑,高層建筑糾傾尚未形成系統(tǒng)的理論和設(shè)計(jì)施工體系。采用ABAQUS軟件模擬某高層基礎(chǔ)少傾側(cè)開挖卸荷溝糾傾技術(shù)實(shí)施情況,得出卸荷溝最優(yōu)深度為20~25m,與建筑最優(yōu)距離為1m。建議卸荷溝開挖厚度為0-2m,與建筑邊緣距離為1m,開挖寬度為20m,開挖深度為15m。
[關(guān)鍵詞]高層建筑; 糾傾研究; 有限元模擬; 卸荷溝法
中圖分類號:TU746-3文獻(xiàn)標(biāo)識碼:A文章編號:1002-848X(2019)08-0130-06
Finite element analysis of excavation unloading ditch method for rectification on less inclined side of high-rise building foundation
Fu Shifeng1,2, Rong Xian1, Li Yurun1
(1 School of Civil and Transportation Engineering, Hebei University of Technology, Tianjin 300401, China; 2 Hebei Academy of Building Research Co., Ltd., Shijiazhuang 050021, China)
Abstract:At present, the rectification technology mainly relies on the past experience to guide the engineering practice. In the past, the object of rectification is mostly multi-storey and low-rise buildings, and there is no systematic theory and design and construction system for high-rise buildings. ABAQUS finite element software was used to simulate the implementation of excavation unloading ditch method for rectification on less inclined side of high-rise building foundation to find the optimal depth of the unloading ditch is 20~25m and the optimum distance from building is 1m. It is suggested that the excavation thickness is 0-2m, the excavation distance is 1m, the excavation width is 20m and the excavation depth is 15m.
Keywords:high-rise building; rectification research; finite element simulation; unloading ditch method