Analysis on construction process of truss string structure
Jiang Ziqin1, Ding Jiemin2, Hu Xiaojuan3
(1 Department of Building Engineering, Tongji University, Shanghai 200092, China;
2 The Architectural Design and Research Institute of Tongji University, Shanghai 200092, China;
3 Chengdu Jizhun Fangzhong Architectural Design Associates, Chengdu 610017, China)
Abstract:Based on the truss string structure of Theme Pavilion for Shanghai World Expo 2010, retrogressive analysis method was adopted to simulate the construction process of the structure. The influence of tension sequence and number of tension steps on the structural performance was analyzed, including internal force and deformation. Contrastive analysis between the numerical values and the theoretical analysis was also considered. The results show that the three-tension-step scheme which tensions the truss string structure step by step can minimize the structure response, including displacement and internal force, which is determined to be the optimal construction scheme of the structure. The construction process simulations of structure can greatly guide the tension of the structure.
Keywords:truss string structure; ten