- 摘 要
-
(1 中衡設計集團股份有限公司, 蘇州 215021;2 施萊希工程設計咨詢(上海)有限公司, 上海 200031)
[摘要]黃金灣旅游綜合體運動休閑中心平面形狀呈8字環(huán)狀,為帶大跨桁架的鋼框架\|支撐體系,整個結構總長約222m,最大寬度82m?;诮ㄖδ艿男枰菝娓叩徒诲e,形成一個8字環(huán)狀滑雪跑道,因此結構多處形成局部錯層。整個結構主要由西側的鋼框架-支撐+均勻分布的鋼框筒以及連接各框筒的大跨桁架構成。結構平面復雜,多種結構體系交錯連接,設計時主要著眼于以下幾點:制定合理的抗震性能目標,確保關鍵構件的抗震性能;均勻布置抗側力體系;優(yōu)化設計大跨度桁架;連接處保證力流傳遞的流暢和合理。此外對大跨度桁架進行了樓板應力分析和舒適度分析。選取關鍵節(jié)點進行了有限元分析,確保關鍵節(jié)點的受力可靠。鑒于結構平面、空間關系復雜,對該項目進行了BIM設計,實現(xiàn)了各專業(yè)協(xié)同設計,提高了管道綜合設計的準確率。
[關鍵詞]黃金灣旅游綜合體; 8字環(huán)狀結構; 抗側力體系; 大跨度桁架; 樓板應力; 舒適度分析; BIM設計
中圖分類號:TU318, TU393-3文獻標識碼:A文章編號:1002-848X(2016)20-0038-07
Structural analysis and design for sports and leisure center of Golden Bay Tourism Complex
Lu Jianglong1, Chen Wei2, Shen Xiaoming1, Yang Lülei1, Zhu Xunyan1, Ai Huijun1
(1 ARTS Group Co., Ltd., Suzhou 215021, China; 2 Schlaich Bergermann und Partner, Shanghai 200031, China)
Abstract:The plane shape of sports and leisure center of Golden Bay Tourism Complex features ‘8’ figure ring structure, and adopts the steel frame-brace system with the large-span truss. The entire structure has the total length of about 222m and the maximum width of 82m. Based on the needs of building function, the roof features ups and downs in elevation to form a ‘8’ figure ring structured skiing track, so there are locally staggered floors in the structure. The whole structure is mainly composed of the steel frame-braces on the west side and the uniformly distributed steel framed tube and the large-span truss connecting each framed tubes. The structure plane is complex, and there is a variety of staggered connected structural systems. The design mainly focuses on the following points: developing reasonable seismic performance objectives to ensure the seismic performance of the key components; evenly arrangement of lateral force resistant system; optimization design of large-span truss; connections to ensure fluency and reasonability of force flow transfer. In addition, the floor stress analysis and floor comfort degree analysis of the large-span truss were carried out. The key nodes were selected to conduct the finite element analysis to ensure the mechanical reliability of the key nodes. In view of the complexity of the structure plane and spatial relation, the BIM design of the project was carried out to realize collaborative design and improve the accuracy of the comprehensive design of the pipeline.
Keywords:Golden Bay Tourism Complex; ‘8’ figure ring structure; lateral force resistant system; largespan truss; floor stress; comfort degree analysis; BIM design
作者簡介:路江龍,高級工程師,一級注冊結構工程師,英國注冊結構工程師,Email:lujianglong@artsgroup.cn。